By using this site, you agree to the Privacy Policy and Commenting Policy.
Accept
Brisbane DevelopmentBrisbane DevelopmentBrisbane Development
  • Areas
    • Brisbane CBD
    • Northern
    • Southern
    • Eastern
    • Western
    • Gold Coast
    • Sunshine Coast
  • Search by Type
    • Residential
    • Residential BTR
    • Commercial
    • Hotel & Resort
    • Brisbane Retail
    • Entertainment / Leisure
    • Infrastructure
    • Concepts
    • Industrial
  • SEQ Development Maps
    • Brisbane Development Map
    • Gold Coast Development Map
  • Major Precincts
    • Brisbane Airport
    • Brisbane 2032 Olympics
    • Northshore Hamilton
    • Queen’s Wharf Precinct
    • Waterfront Brisbane
    • Woolloongabba / Brisbane Live Precinct
Search
  • Advertise
© 2025 Brisbane Development Pty Ltd. All Rights Reserved
Reading: Brisbane’s New Runway enters final construction phase with award of Airfield Contract
Share
Sign In
Notification Show More
Font ResizerAa
Font ResizerAa
Brisbane DevelopmentBrisbane Development
  • Areas
  • Search by Type
  • SEQ Development Maps
  • Major Precincts
Search
  • Areas
    • Brisbane CBD
    • Northern
    • Southern
    • Eastern
    • Western
    • Gold Coast
    • Sunshine Coast
  • Search by Type
    • Residential
    • Residential BTR
    • Commercial
    • Hotel & Resort
    • Brisbane Retail
    • Entertainment / Leisure
    • Infrastructure
    • Concepts
    • Industrial
  • SEQ Development Maps
    • Brisbane Development Map
    • Gold Coast Development Map
  • Major Precincts
    • Brisbane Airport
    • Brisbane 2032 Olympics
    • Northshore Hamilton
    • Queen’s Wharf Precinct
    • Waterfront Brisbane
    • Woolloongabba / Brisbane Live Precinct
Have an existing account? Sign In
Follow US
  • Advertise
© 2024 Brisbane Development Pty Ltd. All Rights Reserved
Brisbane Development > Major Precincts > Brisbane Airport > Brisbane’s New Runway enters final construction phase with award of Airfield Contract
Brisbane Airport

Brisbane’s New Runway enters final construction phase with award of Airfield Contract

Published: 3 July 2017
1 Comment
Share
9 Min Read
new runway under construction
Image of new runway under construction
SHARE

Brisbane Airport’s new runway is on track to open in 2020 with the award of the Airfield Works contract to Skyway, a joint venture (JV) between BMD Construction Pty Ltd and CPB Contractors Pty Limited, a member of the CIMIC Group.

Contents
By the NumbersSouth East Queensland – 89 per centQueensland – 3 per centAustralia – 4 per centInternational – 4 per cent (predominantly airport lighting materials)How Brisbane’s New Runway will be builtPreparation (20 month program*)Pavement Production (21 month program*)Airport Lighting (24 month program*)Airfield (26 month program*) Services and Systems (12 month program*)Navigation Aids (12 month program*)

Both companies have a strong connection to Queensland and to Brisbane Airport.

Julieanne Alroe, Brisbane Airport Corporation (BAC) CEO and Managing Director, said, “Given the long history of this project which had its earliest planning stages in the 1970s, it is a significant milestone to announce today the successful contractor for the largest, final and most expensive package of works to bring Brisbane’s new runway to life.

“That Skyway joint venture partners have a long and storied history with Brisbane Airport, and such strong local pedigree, is particularly pleasing,” Ms Alroe said.

Advertisement

“The new runway was the most important piece of aviation infrastructure being built in Queensland and the biggest undertaken by BAC since the airport was privatised in 1997.

“It is a $1.2 to $1.3 billion privately funded investment that, when operational in 2020, will provide unlimited opportunities for the growth of our city, state and, ultimately, our nation.

Photo of construction work on Brisbane’s new runway

“To put our investment in this project into context, BAC bought the entire airport for $1.38 billion, almost 20 years ago to the day.

“Over the past two decades, BAC has privately invested more than $3.4 billion in upgrading and expanding this critical piece of public infrastructure, with a great deal of this development geared to increasing capacity and improving the travelling experience for airline passengers.

Advertisement

“Importantly, through privatisation, not one cent of the billions of dollars invested in this critical infrastructure has come from the government purse,” Ms Alroe said.

Adolfo Valderas, CIMIC Group Chief Executive Officer, said, “BMD Constructions and CPB Contractors, as the Skyway JV, have brought together a team of expertise and agility to ensure an efficient and cost-effective works program.

“We are committed to ensuring that the project’s planned operational, social and economic benefits are achieved through innovative and sustainable solutions – and that we deliver a quality asset of long-term value for Brisbane Airport and the people of Queensland,” Mr Valderas said.

Advertisement

While BMD Construction is ‘book-ending’ the new runway’s construction, having been a key contractor in the first phase of the project, Joint Venture partner, CPB Contractors, is book-ending the construction of Brisbane Airport proper.

Photo of construction work on Brisbane’s new runway

In the 1980s CPB Contractors was the managing contractor for the construction of the airport as we know it today, overseeing delivery of the runway, taxiways, the Domestic Terminal and the iconic air traffic control tower, all of which opened in 1988.

Brisbane’s new runway is currently the largest aviation infrastructure project under construction in Australia. It includes a 3,300m long x 60m wide runway, over 12km of taxiways, as well as all necessary airfield infrastructure including navigational aids, lighting, multiple utilities, signage, operational roads, drainage, security fencing, control systems and  approx. 300 hectares of airfield landscaping.

BAC’s investment in this final stage of works, including the Airfield Works contract, is worth more than $500 million and will take close to three years to complete.  It is an enormous undertaking with the vast majority of large value components being locally sourced.

Photo of construction work on Brisbane’s new runway

By the Numbers

  • Project expenditure ($) by region – overall breakdown:

South East Queensland – 89 per cent

Peak labour resources – up to 90 per cent is anticipated to be sourced locally:

– 60 managerial, engineering and supervisory staff
– 60 trade level wages employees/ subcontractors
– 150 plant operators
– 130 skilled labour

Plant resources – up to 90 per cent is anticipated to be sourced locally:

– Earthworks/compaction and haulage plant and equipment – 50 excavators, scrapers, compactors and trucks
– Paving equipment – 20 pavers, batch plants and materials handling items
– Construction/ lifting equipment –30 cranes, loaders, piling plant and barges

Queensland – 3 per cent

Australia – 4 per cent

International – 4 per cent (predominantly airport lighting materials)

  • 360 ha site
  • 11 million cubic metres of sand pumped (dredged and hydraulically placed) onto the site – completed in 2014.
  • 330,000 wick drains measuring 8 million linear metres (largest wick drain project in Australia) – completed in 2014.
  • 5,000,000 m3 of earthworks to be manually undertaken on site.
  • 260,000 m3 of topsoil to be generated from on site, supplemented with approx. 15,000 m3 imported from local sources.
  • Up to 300 ha of landscaping, turf and seeds to be sourced locally.
  • 750,000 t of quarry products (sourced and transported locally).
  • 100,000 t of aircraft grade asphalt (prepared on site from local products).
  • 380,000 t of aircraft grade concrete (prepared on site from local products).
  • Up to 1250 million litres of recycled water.
  • 16km of drainage pipes (likely to be local).
  • Over 400 people working directly on the project site during the peak period (this does not include off site client, consultant and supplier jobs, or Dryandra Road work underpass contract, which is employing, at its peak, more than 200).

How Brisbane’s New Runway will be built

Preparation (20 month program*)

  • Set up Compounds for peak 400 workers (water, toilet facilities, offices, crib huts etc)
  • Excavate and remove sand to sand design level (5M cubic metres)
  • Proof roll sand by flooding the sand (with water pumped from Kedron Brook Floodway) and rolling with special rolling machines to consolidate the sand for uniform base material.

Pavement Production (21 month program*)

  • Establish batch plants for concrete, crushed rock and asphalt to form a production line of pavement materials
  • Haul materials from quarries (about total of 1.25 million tonnes) to stockpile on site and feed the production line to make the different pavement layers and the concrete mixtures (different recipes of rock and additive ingredients for each component)
  • Pavement material then placed by paver machines and hand placed – 3.3km runway (mostly asphalt), around 12 km of taxiways (all concrete)

Airport Lighting (24 month program*)

  • Install all airport lighting:
    1. drill holes (over 2000) in pavement every 30m on either side and down the centre of each taxiway and every 15m down the centre of the runway;
    2. place light cans in hole and connect each of them up to their own power source to the side of the runway (part of the 40km of electrical wiring),
    3. build Airport Lighting Electrical Rooms and connect to control systems in the tower
    4. construct HIAL structures into Moreton Bay and at the southern end of the runway

Airfield (26 month program*)

  • Install drainage (open and in-ground)
  • landscaping (including recycled water, onsite topsoil production and turf and stolonisation as designed)
  • Install all Movement Area Guidance Signs (runway system street names)
  • Line marking including runway ends ‘piano keys’, edge lines and hold points

 Services and Systems (12 month program*)

  • Install all other electrical wiring e.g. to all navigation aids, weather instruments etc.
  • Communications fibre ring around the whole airfield; and
  • Control system installation testing and commissioning.

Navigation Aids (12 month program*)

  • Additional clearing and replanting
  • Prepare sites (electrical, water and parking for Airservices to install equipment including: Instrument Landing System (ILS) = Localiser (horizontal) and Glide Slope (vertical), ASMGS (Surface Movement Guidance System), SMR Tower and relay units

* Some stages run concurrently

Inside PsiQuantum’s $1 Billion Plan to Build the World’s First Useful Quantum Computer in Brisbane
Brisbane International Terminal to Get Security & Retail Upgrade
Brisbane Metro Depot Ready for October Launch
Brisbane Airport Unveils $50 Million Parcel Hub: A Game-Changer for Australia Post
Construction to Start on Brisbane Airport Carpark Expansion
TAGGED:Airportbacbrisbanenewparallelrunway

Sign Up to BD Newsletter

Be keep up! Get the latest breaking development news delivered straight to your inbox.
By signing up, you agree to our Commenting Policy and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Whatsapp Whatsapp Email Copy Link Print
Share
What do you think?
Love0
Happy0
Surprise0
Sad0
Angry0
Previous Article Mercedes-Benz store at 300 Adelaide Street Mercedes-Benz to Create CBD Showroom
Next Article the valley live retail and commercial proposal New Mixed Use Development Planned for Bowen Hills
1 Comment
  • Pingback: 3accelerated

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Stay Connected

13kFollowersLike
2kFollowersFollow
6.2kFollowersFollow
3.2kSubscribersSubscribe
LinkedInFollow
Advertisement

Latest News

Architectural rendering of the Stanley Quarter towers from Stanley Street showing the East and West Towers.
Woolloongabba’s Skyline Set to Soar 53 Storeys with Sarazin’s Stanley Quarter East Tower
Featured Residential Southern
12 November 2025
Graya Expands Into High-End Retail Unveiling Koichi Takada Designed ‘James Street Pavilion’
4006 - Newstead, New Farm, Fortitude Valley Brisbane Retail Featured
12 November 2025
Architectural rendering of the external built form of the proposed Spring House project.
Pellicano Lodges Plans For Build-To-Rent Tower In Spring Hill
Featured Northern Residential BTR
6 November 2025
Indicative location map highlighting 176 Montague Road within the broader South Bank expansion precinct.
176 Montague Road Listed Amid South Brisbane’s Next Wave of Development
Industry Content Southern
6 November 2025

Polls

Select two infrastructure projects needed most ahead of the Brisbane 2032 Olympics

View Results

Loading ... Loading ...
  • Polls Archive
//

Brisbane’s leading source of free development and infrastructure news reporting across the greater Brisbane area.

Quick Link

  • ADVERTISE WITH USNew
  • PRIVACY POLICY
  • COMMENTING POLICY
  • CONTACT US
  • MY BOOKMARK

Top Categories

  • BRISBANE DEVELOPMENT MAP
  • BRISBANE CBD
  • QUEEN’S WHARF
  • BRISBANE 2032 OLYMPICS
  • SMART GROWTH SERIES

Sign Up for Our Newsletter

Subscribe to our newsletter to get our newest articles instantly!

Brisbane DevelopmentBrisbane Development
Follow US
© 2025 Brisbane Development Pty Ltd. All Rights Reserved
Join Us!
Subscribe to the BrisbaneDevelopment.com newsletter and never miss our latest news.
Zero spam, Unsubscribe at any time.